DET ER NÅ GJENNOMFØRT FERDIGBEFARING PÅ ALLE TERRASSENE I 1.-4. ETASJE, OG DET ER KUN MONTERING AV NYE REKKVERK OG SKILLEVEGGER SOM GJENSTÅR. DISSE MONTERES FRA LIFT. PÅ GRUNN AV MANGLER I LEVERANSEN, TAR DET FORTSATT LITT TID FØR ALT BLIR FERDIGSTILT. REKKVERK I BF1 C-E MONTERES I DISSE DAGER OG FORVENTES Å VÆRE FERDIG MONTERT MEDIO FEBRUAR.
PLANLAGT FERDIGSTILLELSE AV ALLE ARBEIDER I 1.-4. ETASJE ER SOM FØLGER:
BF1 A-B, MEDIO FEBRUAR
BF1 C-E, ULTIMO FEBRUAR
BF1 F-G, PRIMO MARS
FØR DET MONTERES REKKVERK OG SKILLEVEGGER I UNDERETASJEN, MÅ GULVENE FERDIGSTILLES.
PLANLAGT FERDIGSTILLELSE AV ALLE ARBEIDER I UNDERETASJEN ER SOM FØLGER: BF1 A-B, PRIMO FEBRUAR
BF1 C-E, ULTIMO MARS
BF1 F-G, MEDIO MARS
SÅ SNART KOMMUNEN HAR GITT MIDLERTIDIG BRUKSTILLATELSE VIL SPERRINGEN PÅ DØREN BLI FJERNET.