UKE 12-14:
DET ER NÅ GJENNOMFØRT EN FERDIGBEFARING PÅ TERRASSENE I 1.-4. ETASJE. STILLASEN ER DEMONTERT, SLIK AT REKKVERKENE KAN MONTERES FRA LIFT. FORELØPIG LEGGES DET OPP TIL AT REKKVERKENE MONTERES OG JUSTERES I UKE 13-14.
VI MINNER OM AT BEBOERE FORTSATT IKKE HAR ANLEDNING TIL Å BENYTTE TERRASSENE. DØRENE BLIR SPERRET FREM TIL FERDIGSTILLELSE. AV SIKKERHETSMESSIGE ÅRSAKER MÅ IKKE SPERRINGEN BLI BRUTT.
ETTER AT REKKVERK ER MONTERT I 1.-4. ETASJE, VIL VI FORTSETTE MED UTBEDRING AV TERRASSER I UNDERETASJEN. DET ANBEFALES AT BEBOERNE HOLDER VINDUER, DØRER OG VENTILER LUKKET PÅ DAGTID. ARBEIDET KAN MEDFØRE STØV OG STØY.
Med vennlig hilsen
ALLIERO AS
Anne Lene Aasen Prosjektleder