DET ER NÅ GJENNOMFØRT FERDIGBEFARING PÅ ALLE TERRASSENE I UNDERETASJENE, OG DET ER HOVEDSAKELIG MONTERING AV NYE REKKVERK, SKILLEVEGGER OG DEKKPLATER SOM GJENSTÅR. SKILLEVEGGER OG DEKKPLATER MONTERES FRA LIFT.
PLANLAGT FERDIGSTILLELSE AV OVENSTÅENDE ARBEIDER I BJØRNEFARET 1 ER I UKE 17.
VI FORSØKER Å FÅ REKKVERKENE I UNDERETASJENE PÅ PLASS FØR PÅSKE.
GRUNNMUREN PÅ TERRASSESIDEN SKAL MALES. DETTE GJØRES SÅ SNART VÆR OG ANDRE FORHOLD LIGGER TIL RETTE FOR DET. DET SAMME GJELDER FOR UTBEDRING AV BERØRTE AREALER UTOMHUS.
RISTER TIL RENNENE PÅ TERRASSENE ER UNDER PRODUKSJON. DET ER FORVENTET AT DISSE KOMMER PÅ PLASS I UKE 16/17.
BORETTSLAGET HAR OGSÅ BESTILT FLAGGSTANGHOLDERE TIL REKKVERKENE.
DISSE BLIR MONTERT FØR 17. MAI.
Med vennlig hilsen
ALLIERO AS
Anne Lene Aasen
Prosjektleder