VARSLING VEDR. REHAB. BJØRNEFARET 3

VI ER NÅ I GANG MED KOMPLETTERING AV ALLE REKKVERKENE I 1.-4. ETASJE, MED BÅDE DEKKPLATER OG FLAGGSTANGHOLDERE. PÅ GRUNN AV MANGLER/FEIL I LEVERANSEN OG BEHOV FOR STEDLIGE TILPASNINGER, HAR DET TATT LENGRE TID ENN FORVENTET Å FÅ DETTE PÅ PLASS. DET HAR DESSVERRE OGSÅ PÅVIRKET FREMDRIFTEN TIL TERRASSENE I UNDERETASJENE, HVOR FØLGENDE GJENSTÅR:

  • • MEMBRAN OG FLISLEGGING AV TERRASSEDEKKER
  • • MONTERING AV LISTVERK
  • • MALING/OVERFLATEBEHANDLING
  • • REKKVERK OG SKILLEVEGGER

PLANLAGT FERDIGSTILLELSE AV ARBEIDENE I UNDERETASJENE ER FØLGENDE:

  • • BF3 A-B, MEDIO MAI
  • • BF3 C-E, MEDIO JUNI
  • • BF3 F-G, ULTIMO JUNI

GRUNNMUREN PÅ TERRASSESIDEN SKAL MALES. DETTE GJØRES SÅ SNART VÆR OG ANDRE FORHOLD LIGGER TIL RETTE FOR DET. DET SAMME GJELDER FOR UTBEDRING AV BERØRTE AREALER UTOMHUS.

RISTER TIL RENNENE PÅ TERRASSENE ER UNDER PRODUKSJON, OG VIL BLI MONTERT FORTLØPENDE.

Med vennlig hilsen
ALLIERO AS
Anne Lene Aasen
Prosjektleder